December 22, 2005

CHICAGO -- The Brown Line's Rockwell and Kedzie stations will close for no more than six months starting in late February, a Chicago Transit Authority spokeswoman said Wednesday.

The closures will not occur before Feb. 20, CTA spokeswoman Noelle Gaffney said. In addition, the Kimball and Francisco stations will be shuttered the last weekend of February and the second weekend of March. At some point, those two stations will be closed for four to six months, respectively.

The Armitage, Sedgwick and Chicago stations are scheduled to be closed on the first weekend of March, Gaffney said. Five other weekend closings of those stations will occur at a later date.

The station closings are connected to the CTA's $530 million project to increase capacity and make the Brown Line accessible to the disabled. The project should be done by Dec. 31, 2009.

All told, 15 stations will be closed temporarily, either on weekends or for as long as a year.

 

www.ctariders.org